Bid 25: Res. PB Sample for report
Column Bid Item CT Cost Report by Seq W/SF
Item
Code
Description
Unit
Quantity
Material
Labor
Equip.
Subcontr.
Other
Totals
SF
500
3.001300
15X18 Footing
250.00
LF
30,366.60
30,554.73
188.13
61.11
3.002500
Conc Slab 4''
1,500.00
SF
1,118.15
2,021.15
903.00
4.04
3.003000
Fill Dirt Below Slab Sub
15.00
CF
16.05
16.05
0.03
3.003500
Concrete Steps Sub‑Bid
35.00
LF
374.50
374.50
0.75
3.004800
Sand & Wire Sub‑Bid
2.00
SF
0.74
0.74
3.031100
# 3 (3)Per Run‑Rebar
150.00
LF
15.75
15.75
0.03
3.030100
6X6 10/10 Wire Mesh
5.00
SF
56.70
56.70
0.11
7.023400
R‑19 Walls
2,500.00
SF
918.75
918.75
1.84
7.023700
R‑19 Ceil. Batts
1,500.00
SF
551.25
551.25
1.10
9.010700
1/2Drywall 8'H Intwall
175.00
LF
808.50
808.50
1.62
8.001700
Door‑Ext 3‑0X6‑8 Df 4Pan
1.00
EA
267.50
267.50
0.54
8.010500
Door 2‑6 Pre‑Fit H/C
3.00
HB
240.75
240.75
0.48
8.034300
Door‑Fold 6‑0X8‑0 Hb
2.00
EA
385.20
385.20
0.77
9.000300
Stucco Std.Fin. 9'High
250.00
LF
4,725.00
4,725.00
9.45
*** Bid Total *** =
32,784.50
1,091.13
7,060.94
Material
Labor
Subcontr.
40,936.57
81
Structure SF=
500
2
14
65